Zwartkop Substation Catches Fire

Some parts of Centurion and Pretoria East experienced power supply interruption following the explosion of a 1A Transformer at the Zwartkop Substation, in the early hours of today,
Tuesday, 20 May 2025.

The explosion tripped the Lyttelton Line 1 at Njala, affecting Wingate, Aries and De Hoewes substations.

The City’s Emergency Services Department was dispatched to the scene and swiftly extinguished the blaze.

A team of technicians from Energy and Electricity Department was also dispatched to the scene, and has so far managed to expeditiously energise Wingate, Aries and De Hoewes
substations.

The team is currently assessing the extent of the damage at 1A Zwartkop Substation explosion site as part of the preparations to effect repairs.

The substation will remain off until
the repair work has been completed.
Our technicians will be working tirelessly to ensure that power supply is restored to the affected areas.

The estimated time for restoration will be communicated once the bulk of the
repair work has been completed.

The city apologises to the affected residents for the inconvenience caused by this unforeseen occurrence.

Consumers will be kept abreast of the developments.

Support independent community journalism

Help keep Tshwane Talks free to read

Tshwane Talks stories are free to read, and we want to keep it that way. We ask readers who can afford it to contribute at least R30 a month towards the cost of publishing this independent, non-aligned online newspaper.

Tshwane Talks gives a voice to all sectors of society, irrespective of race, colour, creed, religion or political affiliation.

Contribute by bank deposit

Bank
Standard Bank
Account number
10225548834
Account type
Cheque account
Suggested
R30 or more per month

Questions about contributing? Email info@tshwanetalks.com.

Share your love

Leave a Reply

Your email address will not be published. Required fields are marked *