Q AND A WITH DPWI REGARDING COMPLETION OF MAMS EAST COURT
The entrance of the unfinished Mamelodi East Magistrates Court photo by Peter Mothiba
The Mamelodi East Magistrates’ Court building has been under construction for more than 13 years now (since 2013) and progress in this regard has since then been marred by contractual disputes between the contractor and the Department of Public Works and Infrastructure (DPWI) on the one hand, as well as disputes between the contractor and a group of gangsters on the other hand demanding a 30% share from the contractor.
A new contractor has now been appointed and work has resumed at the court building.
The following is a Q and A session with the Department of Public Works and Infrastructure (DPWI).
Project: Completion of the Mamelodi Magistrate’s Court
1. Who was appointed?
– *Musan Trading Enterprise* — appointed August 2026 via open tender
– Site handed over, work started *7 October 2026*
– Department’s in-house Architect is principal agent, original engineering consultants remain
2. How much?
– *R241,258,229.61 including VAT*
– No payment made yet — still in first month of work
3. What will be done?
Two-storey building with 16 courtrooms, judicial/admin offices, holding cells, child witness facilities, basement with 27 parking bays.
Structure is built and roofed.
New contract covers:
– Internal finishes, electrical, standby generator + solar PV
– Aircon, fire protection, plumbing/drainage, 3 passenger lifts
– ICT networks and court recording systems
– External works: access road, upgrade of Tsamaya Ave / Eerste Fabriek Rd intersection, stormwater, water/sewer, parking, landscaping
– Repairs for theft/vandalism damage + redoing sub-standard work from previous contractor
4. When will it finish?
– 24-month contract — completion due *8 October 2028*, then commissioning and handover to Department of Justice and Constitutional Development
5. Measures against 30% disruptions?
– Community Liaison Officer + Project Steering Committee (community structures + ward reps) selected as formal channel
– Contractor must table subcontracting + local labour plans to Committee — 27 local workers employed, 2 subcontractors appointed already
– Security plan agreed with SAPS — threats/disruption/extortion to be reported for criminal action
6. Action against previous contractor?
– Fikile Construction — entered business rescue Oct 2020, failed to progress.
Final warning 14 Sept 2023, contract terminated 27 Oct 2023. Building was ∼60% complete.
– Letter of demand issued to recover additional costs
– State Attorney instructed to issue summons — loss to be quantified now that completion contract is awarded
– Submission to restrict company from doing business with the state being processed.
Support independent community journalism
Help keep Tshwane Talks free to read
Tshwane Talks stories are free to read, and we want to keep it that way. We ask readers who can afford it to contribute at least R30 a month towards the cost of publishing this independent, non-aligned online newspaper.
Tshwane Talks gives a voice to all sectors of society, irrespective of race, colour, creed, religion or political affiliation.
Contribute by bank deposit
- Bank
- Standard Bank
- Account number
- 10225548834
- Account type
- Cheque account
- Suggested
- R30 or more per month
Questions about contributing? Email info@tshwanetalks.com.